VOL 11 | NUM 42 | 9 May 2025
|
|
|
|
|
|
|
|
CHILE | 28 April - 4 May 2025
|
|
|
|
Power Markets Weekly
is a brief weekly review of the electric market operation in Chile, Mexico, Iberia, France and Italy. If you are not a subscriber, please feel free to subscribe
here
|
|
|
|
|
|
DNV offers tools for Wholesale Market analysis and operation:
- DNV Power Analytics (DNV-PA) is our web-based platform that provides access to constantly updated long-term energy price forecasts.
- With a refined design and an improved user experience we are upgrading our digital services for our customers.
|
|
|
|
|
|
|
Weekly curtailment rate hits the lowest value of the year, leading to a solar share increase
|
|
|
|
Polpaico average price was USD 67/MWh, 26% lower than last week’s and 13% higher than the same week last year.
|
|
Marginal cost evolution in Polpaico during past years
|
|
|
|
|
|
|
In terms of the energy mix, solar participation rose this week by 3.5 pp., being the main increase of the week. This, coupled with the maintenance of some gas power plants, led to a 0.5 pp. decrease in gas generation. Coal and dam followed solar with increases of 0.6 pp. and 0.4 pp., respectively.
|
|
On the other hand, renewables technologies like wind and run-of-river decreased their shares, the first one by 2.0 pp. and the last by 0.6 pp.
|
|
Demand reached its weekly peak of 11.3 GWh/h at 1 PM on Wednesday, when solar generation represented 44.3% of the mix, while wind represented 11.7%. Hydro sources represented a combined 18.2% and thermal sources a combined 23.2%.
|
|
Generation Mix
|
|
|
|
|
Variation
|
|
|
|
|
Power range by energy sources (average prices)
|
|
|
|
|
|
|
|
|
|
|
|
Geothermal
|
|
Cogeneration
|
|
Biomass
|
|
Coal
|
|
|
Gas
|
|
Oil
|
|
BESS
|
|
Dam
|
|
|
Run-of-river
|
|
Wind
|
|
PV Solar
|
|
CSP
|
|
|
|
|
|
On the transmission side, the common decoupling of Puerto Montt was observed at different hours from Monday to Thursday and on Saturday due to congestions on the 220 kV lines: Charrúa - Santa Clara and Lastarria – Ciruelos. Additionally, there were congestions on the 500 kV line Nueva Pan de Azúcar – Polpaico, which decoupled Pan de Azúcar from Polpaico during solar hours on Tuesday, Wednesday, and Friday.
|
|
At nigh times from Monday to Saturday, different oil power plants had to operate to meet the demand and supply ancillary services, and at 11 PM on Tuesday the weekly peak marginal cost occurred, reaching USD 199.0/MWh on Crucero and USD 198.5/MWh on Polpaico when Espinos power plant (oil) set the price. Tuesday evening was also coincidentally the moment where wind generation and share reached their lowest.
|
|
Although water variable cost was reduced this week from USD 94/MWh to USD 76/MWh, some dam power plants faced reservoir level controls, and two dam power plants were declared under depletion: Pehuenche during the whole week except from Thursday and Rapel on Wednesday and Friday.
|
|
|
|
|
|
|
Crucero
USD 66.0/MWh
|
|
D. de Almagro
USD 64.6/MWh
|
|
Pan de Azúcar
USD 64.7/MWh
|
|
|
|
|
Polpaico
USD 67.0/MWh
|
|
Charrúa
USD 64.5/MWh
|
|
Puerto Montt
USD 64.8/MWh
|
|
|
|
|
|
Solar and Wind production & BESS dispatch
|
|
Solar generation increased this week by 55 GWh (+19.7%). Main plant factor was seen in both Crucero and Diego de Almagro area with an equally 20.4%, while the lowest plant factor was seen in Puerto Montt (6.2%).
|
|
Wind generation on the other side, dropped by 31.8 GWh (-13.9%). Main power plant factor was seen in Puerto Montt with 31.2%, while the lowest was seen in Diego de Almagro with 14.0%.
|
|
BESS injections increased by 3.8 GWh (+12.3%). Highest plant factor was seen in Crucero area, with 21.7%, while the lowest was in Polpaico with 5.9%.
|
|
This week’s curtailment rate for solar was of 3.9% (13.6 GWh), while wind curtailment only reached 2.4% (4.8 GWh), reaching the lowest average combined weekly curtailment rate of the year so far: 3.4% (18.4 GWh), this is 61.4 GWh less than last week.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Crucero
USD 23.4/MWh
|
|
D. de Almagro
USD 21.7/MWh
|
|
Pan de Azúcar
USD 21.2/MWh
|
|
|
|
|
Polpaico
USD 23.1/MWh
|
|
Charrúa
USD 22.7/MWh
|
|
Puerto Montt
USD 38.7/MWh
|
|
|
|
|
Energy weighted average spot price using PV production by zone
|
|
|
|
|
|
|
Crucero
USD 60.3/MWh
|
|
D. de Almagro
USD 66.6/MWh
|
|
Pan de Azúcar
USD 59.2/MWh
|
|
|
|
|
Polpaico
USD 65.9/MWh
|
|
Charrúa
USD 63.7/MWh
|
|
Puerto Montt
USD 58.8/MWh
|
|
|
|
|
Energy weighted average spot price using wind production by zone
|
|
|
|
BESS discharge capture price
|
|
|
|
|
Crucero
USD 101.4/MWh
|
|
D. de Almagro
USD 83.3/MWh
|
|
Pan de Azúcar
USD 107.3/MWh
|
|
|
|
|
Polpaico
USD 112.8/MWh
|
|
Charrúa
USD 102.6/MWh
|
|
|
|
|
Energy weighted average spot price using BESS injection by zone
|
|
|
|
|
|
DNV, Magdalena 181, Las Condes, Santiago, Chile
|
|
|
|
|
|
|